Wednesday, July 9, 2008

Interior lodge work

Thought it was time for a lodge addition update as it has been a while since I blogged. The plumber is done with all that he can do on the interior until he can install fixtures which will only be done once the carpenter is done. The electrician is moving along. He has the entrance completed so the carpenter this week got all the interior walls insulated and soon they will start with the knotty pine on the walls and ceiling in the 14 foot vaulted ceiling entrance which will be used for our summer and winter ticket sales as well as our retail sales. I will get some photos of the knotty pine once it is done........really, I will!

Later......
ps. the full service river floats are going gang busters again. Goood Hotttt Summer days is what everybody was waiting for and now it's here......plus the flood to be behind us!