Wednesday, November 19, 2008

Another Chairlift Update

Progress continues........

Monday November 17 - towers 4, 5, and 6 were set in place......see pics

Tuesday November 18 - the holes were dug for the top bull wheel tower and strut

Wednesday November 19 - 30 yards of concrete were poured around the top bull wheel tower and strut..........30 YARDS - thats four concrete truck loads --- BIG....and the last of the concrete pouring for this project!


Tomorrow we plan to set the motor room on top of the gantry and then start setting the last three towers. Stay tuned...